Judgement expected Wednesday in Record Ridge case

A judge is expected to rule Wednesday at 1:30 p.m. on whether a proposed open-pit magnesium project southwest of Rossland should be suspended pending a judicial review.

Arguments in the case wrapped up this afternoon. A lawyer for the company involved asked that a petition from the Save Record Ridge Action Committee be dismissed with costs.

In her submissions, Carina Chiu argued that granting an injunction would harm West High Yield’s business operations. She said the company would have to cancel a contract with the Osoyoos Indian Band and a company that has been providing pre-construction services. She added the company has been told that if the project doesn’t go forward this spring, its prospective mine managers will look for work elsewhere.

Chiu said West High Yield has spent $740,000 since last fall in preparation costs and is finalizing a loan of $30 million for construction. She said any delays will result in “significant” interest charges and hamper ore deliveries, affecting the company’s ability to generate cash flow this year.

Save Record Ridge is seeking an injunction stopping the project until a judicial review can be heard. They want to overturn the provincial Environmental Assessment Office’s decision not to subject the project to a full environmental review, but the matter isn’t scheduled to be heard until August.

Following Justice Dev Dley’s urging Monday, the case might be moved up to May, but Save Record Ridge lawyer Ben Isitt said an interim order will still be needed to prevent “irreparable harm” if the company is able to begin work in April. He said they want to prevent any blasting, excavating, or logging.

Chiu said she didn’t agree with the suggestion that another lawyer for the company was solely responsible for delaying the case. She said offers had been made to move the matter to another location. However, Dley said from his reading of correspondence presented to him, the company’s lawyer never offered to be available earlier than August.

“It seems the petitioner [Save Record Ridge] was trying to do everything possible to get the matter on and didn’t care where they had to go,” he said. “It doesn’t sound as if [the company’s lawyer] was prepared to do much of anything to accommodate.”

Dley said it would be to the company’s advantage to have the judicial hearing put off until a significant amount of work is done, by which time the case will be moot.

In other submissions, Chiu said the court should ignore evidence presented by the Sinixt Confederacy in support of Save Record Ridge’s petition, because the Sinixt are technically a respondent in the case instead of a co-petitioner. Julia Riddle, a lawyer for the Sinixt, argued otherwise, suggesting the company’s view was “premised on a fundamental misunderstanding of the rules.”

Chiu further noted that while West High Yield already has its mining permit, it still needs to receive other permits from various government ministries before it can proceed. She said while the company expects to have all of those permits by April, there is no guarantee.

She argued Save Record Ridge “must demonstrate the harm is imminent and highly probable,” but because ground can’t be broken until the other permits are approved, the group’s application is merely “speculative,” which isn’t enough for an injunction.

Earlier today, Solomon Kay-Reid, representing the Ministry of Environment and its chief permitting officer, said the government doesn’t take a position on whether the work should be delayed pending the judicial review.

But he said the court should be “cautious” with Save Record Ridge’s arguments of “irreparable harm” because some of their concerns will be addressed by permits that haven’t yet been issued, while others are already addressed by conditions in the company’s mining permit.

In his closing submission, Isitt responded that even if the company complies with its permits, irreparable harm may still occur because once a project starts, it would no longer be subject to an environmental review, regardless of the outcome of the judicial review.

Isitt also provided an update on Save Record Ridge’s finances, after the judge questioned Monday whether the $60,000 they have in hand is enough to provide a security deposit in case they lose the judicial review.

Isitt said after putting out another call to supporters, the organization had collected another $138,000 in pledges by this afternoon. But he said while the group might be on the hook for damages if they are unsuccessful, a security deposit isn’t normally required. Riddle, the lawyer for the Sinixt Confederacy, also argued against imposing such a security.

Chiu said potential damages to the company if the project is delayed are “not in the tens of thousands. We are well beyond that.”

Greg Nesteroff
Greg Nesteroff
Greg has been working in West Kootenay news media off and on since 1998. When he's not on the air, he's busy writing about local history. He has recently published a book about the man who founded the ghost town of Sandon.

Continue Reading

cjat Now playing play

ckqr Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Castlegar municipal election turnout up from 2022

According to a report from chief election officer Nicole Brown, 2,039 out of 6,416 eligible voters cast ballots, which is 31.8 per cent.

Jan Morton recognized by BC Non-Profit Housing Association

The founding president of the Lower Columbia Affordable Housing Society is this year's recipient of a lifetime achievement award.

Castlegar wants help shaping parks and trails

The City of Castlegar is asking residents to share their feedback, experiences, ideas, and priorities for local parks and trails as community engagement gets underway for the city’s first parks and trails plan.

Ootischenia septage ponds hit capacity

The Regional District of Central Kootenay (RDCK) is moving ahead with upgrades to its Ootischenia Landfill septage ponds, which have reached capacity.

New public safety warning system added at Waneta dam

Starting next week FortisBC will begin testing new audio and visual warnings to complement existing signage and provide additional warning when water levels below the dam are about to change.
- Advertisement -