Castlegar to borrow $1 million for sewage plant work

The City of Castlegar will borrow close to $1 million to get a head start on improvements to the south sewage treatment plant, which has been plagued with problems in recent years.

The city plans to bring one of the plant’s two bioreactors back online. It has been out of commission since 2008. The city says that will improve flow through the system and give operators more breathing room to meet permit requirements and protect the Columbia River from accidental spills of undertreated sewage.

A construction management contract was awarded last March to Chandos Construction LP, valued at over $6.8 million. Staff say while design work has already started, the loan will let them order equipment with long lead times for delivery.

The project will require further borrowing that will be subject to a counterpetition, but the city says that process could take up to six months. To get going, council last week approved the interim borrowing, to be repaid in five years.

The city’s long-term sewage plan calls for the city’s two sewage plants to be consolidated at the north-end site at a cost of up to $82 million, but that could be up to 15 years away.


Be the first to know! Don’t miss out on breaking news and daily updates in your area. Sign up to MyKootenayNowNews Alerts.

Continue Reading

cjat Now playing play

ckqr Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Trail facing 5.5% utility rate increase

Residents are looking at paying another $52 for water and sewer service in 2027.

Judicial review of Record Ridge mining permit delayed

The case was expected to be heard starting next week in Rossland. But the matter has been rescheduled to the last week of February.

Indigenous partnership closes Coastal GasLink investment deal

Twelve northern B.C. First Nations have closed a deal with TC Energy to take an economic interest in part of the company's stake in the Coastal GasLink pipeline.

UBCIC Grand Chief warns of legal battles as B.C. government moves to repeal DRIPA

Grand Chief Stewart Phillip says the B.C. Conservative government's plan to repeal the province's landmark reconciliation legislation will lead to more uncertainty and "protracted" legal battles.

Eby absent as 26 Opposition New Democrat MLAs sworn in

Most B.C. New Democrat MLAs were sworn in during a ceremony at the legislature on Thursday, but David Eby was absent.
- Advertisement -