Trail water project timeline extended

Residents of Shavers Bench, Miral Heights and Glenmerry will be supplied by the Trail’s Water Treatment plant for two and a half months longer than originally planned.

Staff completed work at the Beaver Creek Well that forced the initial shut down but discovered a need for an emergency fix to a water main.

This means all residents will still receive water from the main plant into the warmer months of May and June.

Utilities Superintendent Chris McIssac says it will be a concern if work goes past that time.

The initial upgrades to the pump house will allow for the Green Gables reservoir to go to full capacity.

Continue Reading

cjat Now playing play

ckqr Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

B.C. adds 5k jobs in June, led by gains in part-time work

British Columbia added 5,000 jobs in June but saw a dip in full-time employment, according to the latest jobs report from Statistics Canada. 

B.C. adds 5k jobs in June, led by gains in part-time work

British Columbia added 5,000 jobs in June but saw a dip in full-time employment, according to the latest jobs report from Statistics Canada. 

B.C. maintains decision to end drug coverage for girl with rare, fatal disease

B.C. is standing by the decision not to continue drug coverage for a Vancouver Island girl with a rare, fatal disease. 

Measles cases reported in B.C. this year top 100

B.C.’s health officials have said 102 cases of measles have been reported across B.C. so far this year, with most of those in the Northern Health region.

Rossland mom checks off English Channel swim

It has been a long time coming, but as of June 29 Rossland’s Aerin Bowers has officially completed her swim across the English Channel.
- Advertisement -