The company that wants to start an open-pit magnesium mine near Rossland says it will appeal a judge’s decision this week to grant an injunction stopping the project until a judicial review can be heard.
In a news release, West High Yield said it has filed leave to appeal. It said it believes the regulatory approvals obtained for the project were properly issued and that it “intends to continue fully defending its position through the legal process.”
It wasn’t immediately clear how quickly the appeal might be heard.
On Wednesday, Justice Dev Dley approved an injunction that temporarily prevents work like blasting, excavation, and logging at the proposed mine.
West High Yield said it will also seek a review of the security deposit that the Save Record Ridge Action Committee was ordered to post in connection with the injunction. Dley set the amount at $162,500, which the company said is not enough relative to the potential damages associated with the delay.
The company says it wants to seek an increase to “more appropriately reflect the potential financial impacts,” in light of an agreement announced this week with Galaxy Trade and Technology, an American-based magnesium supply company.
According to a news release, Galaxy will buy ore from the project over two years with an option to extend the agreement for another nine years. The deal calls for a $5 million US deposit to fund initial deliveries.
West High Yield also said this week it has received a draft access permit from the Ministry of Transportation, governing traffic from its mine onto provincial highways. It’s one of a few outstanding permits the company was hoping to secure before the start of April, when its mining permit allows work to begin.
Before the appeal was announced late Thursday, a spokeswoman for Save Record Ridge said Dley’s ruling was all they could have hoped for. “It was such a reasonable weighted decision,” said Melanie Mercier. “I couldn’t be more pleased.”
Dley also ordered the judicial review be held in Rossland in early May. Previously it had been scheduled for August in Nelson due to the unavailability of a lawyer for the mining company. Mercier said she was happy the hearing has been sped up, although it didn’t come as a surprise, since during the hearing this week the judge asked the parties to look at earlier dates.
The review will examine the provincial government’s decision not to subject the mine to a full environmental review. The chief permitting officer said the project falls below a certain output threshold that would trigger a review. However, opponents argue that while the proposed tonnage has been reduced from previous proposals, the mine’s overall footprint would be about the same. Once the project is substantially started, it would no longer be subject to an environmental review.
Mercier said they are prepared for the case, which could set a precedent.
“This judicial review is expected to examine how the Environmental Assessment Act is applied in British Columbia and whether projects of this scale must undergo environmental review before construction begins,” she said. “It’s an opportunity to show that this case goes far beyond Rossland. We’re really excited about that.”
Mercier was further happy the judge insisted the case be heard in Rossland, rather than moved out of area to accommodate the mining company’s lawyer.
Although the company is seeking to have the injunction set aside, it said that it “looks forward” to the expedited judicial review in May.
When the judge doubted that the $60,000 Save Record Ridge had on hand would be enough of a security deposit for damages in case they lose the review, the group put out a call to supporters, who quickly added over $100,000 in cash and pledges.
“An incredible amount of pledges came through in less than 24 hours,” Mercier said. “I’m still overwhelmed by that. I feel our community is behind us. The show of support is immense and I couldn’t be more grateful.”
The judge ordered $60,000 in the group’s bank account to be frozen and gave them two weeks to produce the rest. Mercier said she believes they’ll be able to meet that deadline.
The mine site is about seven kilometers from Rossland.