Future student housing for Selkirk College stacking up

With the foundation laid for 150 new beds of student housing at Selkirk College, the projects at the Silver King campus in Nelson and the Castlegar campus are taking a dramatic leap forward.

The modular build process being used in the construction of the $33.9 million project saw the Silver King campus three-storey building erected quickly in early May and the massive crane used to stack the pre-fabricated rooms is now on standby for the Castlegar campus where it will be used for a similar outcome in mid-June.

“There is a Lego feel to it,” says Stephen Monahan, Selkirk College’s manager of capital projects. “This is an efficient way to build housing of this type and as the project progresses, we are seeing those advantages.”

The finished project, funded by the provincial government along with a $1.65 million contribution from the Columbia Basin Trust, will increase on-campus housing at Selkirk College by 71 per cent. Once complete, the Silver King campus will have 35 units available for students and the Castlegar campus will add 112.

The project broke ground in November 2022 under a design-build contract with Scott Builders. After months of work preparing the foundation at both sites, the modular units began arriving on transport trucks to the West Kootenay earlier in the spring from southern Alberta where they were fabricated by ROC Modular.

Built indoors at a massive temperature-controlled facility in the community of Bow Island, the modular units come complete with drywall, insulation, windows, cabinets, interior paint, electrical/plumbing and flooring. A crane is used to stack the modular units in a process that takes only a few days. The modular units are then sealed and weatherproofed in preparation for the next phase of construction.

The project includes 18 subtrades with approximately 90 individual workers on-site between both locations. Over the coming months, the local subtrades will continue to build the corridors between the modular units, add the siding/roofing, construct many of the common areas, landscape and complete all the details that will result in the much-needed housing units.

Working with Nelson-based Fuhrious Construction Ltd., Dannica Lampron is part of the sub-trade crew who helped with the foundation pours and will continue to work on the project in the coming months. After completing Selkirk College’s six-month carpentry foundation program in January, Lampron was hired by Fuhrious Construction as an apprentice where she is working towards the ultimate goal of Red Seal carpenter.

“It was very hard work and character building, but it was sweet,” Lampron says of the foundation component that was completed just a few steps from the Silver King campus shop space where she was a student. “As an apprentice, it’s important to gather a variety of skills and work on a variety of projects. Getting to be part of this particular project is a great way to continue with my education.”

The project is expected to be complete in early 2024 with full operation at both campuses in September 2024.

BY THE NUMBERS:

  • 42 modular units in total (12 at Silver King and 30 at Castlegar)
  • 8 types of modules at Castlegar and 7 types of modules at Silver King, including everything from student rooms, study rooms, kitchens, laundries, stairs and mechanical/electrical space.
  • One module can contain as many as six student rooms
  • 82 washrooms (21 at Silver King and 61 at Castlegar)
  • 150 beds (114 at Castlegar, 36 at Silver King)
  • 3 family accommodation rooms (2 at Castlegar, 1 at Silver King) and 6 accessible rooms (4 at Castlegar, 2 at SK)
  • 6 communal kitchens (3 at each
  • 402 doors (115 at SK, 287 at Castlegar)
  • 339 pages of design drawings. (137 for Silver King, 202 for Castlegar)

Continue Reading

cjat Now playing play

ckqr Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

WINS busy as campaign begins against gender-based violence

A woman who has been involved with the WINS Transition House in Trail for nearly 30 years says she sees some discouraging signs as the community prepares to mark the national 16 Days of Activism Against Gender-Based Violence.

Report alleges ChatGPT gave Tumbler Ridge advice on making 3D-printed weapons

ChatGPT gave the Tumbler Ridge shooter advice on how to assemble and use 3D-printed weapons accessories and engaged in graphic violent fantasies in the months leading up to February's mass shooting, a new media report alleges.

BC Green MLAs sworn in, pledge to hold Conservative government to account

B.C. Green Leader Emily Lowan said she is committed to holding the new B.C. Conservative government to account, as she was sworn in as an MLA for the first time on Monday.

UPDATED: Castlegar grad parents group allegedly defrauded

The parent grad committee at Stanley Humphries Secondary in Castlegar says its money has been "misused" by a former executive member.

Jan Morton recognized by BC Non-Profit Housing Association

The founding president of the Lower Columbia Affordable Housing Society is this year's recipient of a lifetime achievement award.
- Advertisement -